YEREVAN, APRIL 13, NOYAN TAPAN. The new building of the
court of first instance of Yerevan's Shengavit community was
delivered for operation on April 12. According to the RA
Minister of Justice David Harutyunian, the putting of this
building into operation completed the first stage of
construction or reconstruction of the buildings of 14 courts
under the credit program on court and legal reforms.
The building's main entrance, which is meant for court
visitors, also has a ramp for wheelchairs of disabled persons
with movement problems. The building is provided with all the
necessary communications: a new power substation, a autonomous
boiler-house, gas supply and water supply systems, as well as
sewerage pipes. There is an air circulation system in the court
building. The air circulation in halls is done by a channel
method, which ensures re-circulation and outflow of the air.
Air circulation of accused persons' cells is done by the
split system. All offices have air conditioners on their
windows.
The court building is designed for 7 judges and has 6
furnished courtrooms, one of which - the courtroom for holding
sittings on civil cases has additional equipment to ensure
safety of judges and court case participants. The public section
and the sitting section of this courtroom are separated from
each other by a staned-glass window to ensure acoustic
insulation. Direct audio reports about sittings are transmitted
by loudspeakers to the public section of the courtroom.
According to the justice minister, other courts may make use of
this courtroom in case of necessity.
The cost of the court building's construction made 410,
854.2 thousand drams. Financing was done with World Bank credit
resources (90%) and funds of the RA state budget (10%).