Construction work of new power unit of Yerevan TPP proceeds
according to schedule
05-06-2009 18:00:00 | Armenia | Economy
YEREVAN, JUNE 5, NOYAN TAPAN. The construction work of the
new power unit of Yerevan Thermal Power Plant (TPP) is
proceeding according to the schedule, and the degree of
construction work implementation is assessed at 68%, RA Minister
of Energy and Natural Resources Armen Movsisian told reporters
during the June 3 visit to Yerevan TPP with the aim of
familiarizing himself with the construction process of the new
power unit.
In his words, all building and assembly work has to be
completed by October, after which the work on putting the TPP in
order will start. The completion of construction work and the
launching of Yerevan TPP is scheduled for April 30, 2010. A.
Movsisian said the equipment was mainly imported, with heavy and
big equipment being imported by Mria plane with the greatest
aircraft capacity in the world. By an agreement, all equipment,
including machinery of over 240 tons, will be brought into
Armenia by mid July.
The overall intsalled capacity of the power plant will make
271.8 megawatts, including electric capacity of 242 megawatts,
and TPP efficiency of 68%. It will consume natural gas 2-2.3
times less for generation of 1 kwh of power compared to other
thermal power plants in Armenia. The control of Yerevan TPP: its
launching, connection to the network, loading and stoppage will
be fully automatic. Its maintenance staff will make about 50
persons. Under the program it is envisaged training of new
experts at Alstom, Fuji and SEC companies.
The minister said that the global financial crisis has not
had and will not have any impact on construction of the power
unit.