SOLDERING WORK ALMOST COMPLETED ON ARMENIAN SECTION OF
IRAN-ARMENIA GAS PIPELINE
23-02-2007 18:30:00 | Armenia | Economy
YEREVAN, FEBRUARY 23, NOYAN TAPAN. Unfavorable weather
conditions prevented the Iran-Armenia gas pipeline from being
put into operation ahead of the date envisaged by the agreement
- March 17. Director of High-Vaoltage Electric Networks company
Sahak Abrahamian told NT correspondent that only soldering work
remains to be done on 2.5 km of the gas pipeline's 40 km
Armenian section.
The Armenian delegation headed by the RA Minister of Energy
Armen Movsisian will leave for Iran on February 26 in order to
discuss issues related to operation of the gas pipeline.